Migration Advisory

Migrating from another VDI solution

Organisations replacing an existing Citrix, VMware Horizon, or Microsoft RDS deployment with Accops Workspace should plan the migration in phases:

Phase Activity
1 — Assessment Inventory existing pools, application assignments, user groups, and connection profiles
2 — Parallel deployment Stand up Accops alongside the existing solution; do not decommission yet
3 — Pilot migration Move a pilot group (10–20 users) to Accops; run both systems in parallel
4 — Wave migration Migrate remaining users in waves, prioritising low-risk groups first
5 — Decommission Power down old infrastructure only after all users are validated on Accops

Key considerations

Master Image: Build a fresh master image rather than converting existing VM templates. Convert the Gold Image using HyWorks DVM Tools rather than reusing the old broker's sysprep image.

Profiles: If users have roaming profiles, continue using the same profile share — HyWorks connects to the same Windows profile store.

Applications: Applications installed on the old SHD/RDS servers must be reinstalled on the new HyWorks Session Host Servers. Use the same application deployment process (GPO/SCCM/Intune) as the previous environment.

Network: HySecure replaces the VPN or SSL gateway. Decommission the old gateway only after the HySecure pilot is stable.


Export/Import configuration

HyWorks supports configuration export — useful for replicating a working setup to a new controller node during migration.